§ 9.1. Application process.  


Latest version.
  • If a permit is required prior to beginning work, the applicant shall prepare a drawing of the proposed work showing the location and details of such work. This shall be submitted to the county at least two weeks prior to the date the permit is desired. Simple service connections will be given a high priority and will be returned within seven days.

    This permit shall be kept at the work site at all times while said work is under way and must be shown to any representative of the county or law enforcement officer on demand.

(Ord. No. 91-3, § 12, 5-20-91)