Appendix A.
Latest version.
PERMIT FEES ADMINISTRATIVE FEE $20.00 in addition to below fees on all permits. BUILDING/CONSTRUCTION/MECHANICAL/
PLUMBING/GAS/ELECTRICAL/MISC.$0.00 to $2,000.00 $80.00 $2,001.00 to $5,000.00 $104.00 $5,001.00 to $10,000.00 $157.00 $10,001.00 to $40,000.00 $157.00 for the first $10,000.00 plus $11.00 for each additional thousand or fraction thereof, to and including $40,000.00 $40,001.00 to $100,000.00 $487.00 for the first $40,000.00 plus $9.00 for each additional thousand or fraction thereof, to and including $100,000.00 $100,001.00 to $500,000.00 $1,027.00 for first $100,000.00 plus $7.00 for each additional thousand or fraction thereof, to and including $500,000.00 $500,001.00 to $1,000,000.00 $3,827.00 for the first $500,000.00 plus $5.00 for each additional thousand or fraction thereof, to and including $1,000,000.00 $1,000,001.00 to $5,000,000.00 $6,327.00 for the first $1,000,000.00 plus $3.00 for each additional thousand or fraction thereof, to and including $5,000,000.00 $5,000,001.00 and over $18,327.00 for the first $5,000,000.00 plus $2.00 for each additional thousand or fraction thereof ELECTRICAL RECONNECT FEE
(Reconnection Only/ Must Obtain Electrical Permit If Work Is Done)$25.00 MOVING FEE For the moving of any building or structure $100.00 DEMOLITION FEE Inspection Fee $100.00 MOBILE HOME INSPECTIONS Inspection Fee $100.00 REINSPECTIONS Additional Required Inspections (Due to deficient or defective work or through fault of permit holder or his employee) 1 st Reinspection $25.00 2 nd Reinspection $50.00 3 rd or more Reinspections $100.00 PLAN REVIEW Fee for required plan reviews will be 50% of total permit fee APPEALS BOARD FEE For any construction board of appeals application $300.00 COPIES Copies of any files/ordinances/etc. will be $1.00 per page
(Ord. No. 13-17, § 4, 8-19-13; Ord. No. 17-08, § I, 9-19-17 )
Editor's note
As a part of Supp. No. 34, at the direction of the county, app. A was amended to read as set out herein.